Solar Project Phases 1 and 2

Solar Panel Installation
Posted on 03/08/2018
There will be two more phases to complete the solar panel project at FWHS.  This will affect parking on campus in the following ways:






Phase 1:
 March 12 through April 6 - CLOSED FOR PARKING

The north/south running rows of parking in the north faculty parking lot.

The middle strip of parking between athletics and the 40's classrooms.

The parent drop off/pick up lanes next to athletics.

The north/south running row of parking directly in front of athletics.  Will temporarily serve as the parent loading zone before and after school.

The center square of the bus bay.

Solar Project Phase 1


Phase 2: April 9 through May 11 - CLOSED FOR PARKING

The north/south running row of parking directly in front of athletics.

The two north rows of the student parking lot.

The center square of the bus bay.

Solar Project Phase 2

 During each phase we will temporarily lose approximately 50 parking spaces but we should have enough for everyone.  The front square of parking next to the PDC can also be used for parking as an overflow location.  The outlined red areas are construction zones which are completely off-limits.

Once the project is complete parking availability will resume regularly, with the exception that you will have many options for covered, energy-efficient parking!  If you have any questions let us know, and thank you for your patience as we finish a lengthy, but ultimately rewarding project.